TURKEY - BTC REPAIR AND ENHANCEMENT PROJECTS

Tekfen Job No:

363

Location:

Turkey Section of BTC Crude Oil Pipeline System

Client:

BTC Co.

Contractor:

Tekfen Construction and Installation Co., Inc.

Tekfen Portion:

100%

Commencement:

01/02/2018

Completion:

01/02/2021

Project 363 BTC Repair and Enhancement Project have been signed on the 1st February of 2018 with the client BTC Co., as a follow up project to Project 340. Tekfen will be responsible for executing many challenging works during the contract period as it has been since 2007. These challenging works will be executed on a very large geography. The contract for Project 363 will be expired by the 1st February of 2021.

Major works in the scope of Project 363;

Pipeline Re-routings
River Crossing Works
Spool Production - Installation and Valve Replacement Works At Pump Stations
Seismic Investigation Works
Perimeter Intruder Detection System Enhancement Works
Pump Stations Fire Fighting Improvement Works
Security System (PIDS & CCTV) Enhancement Works
UPS Replacement Works
Various Mechanical and Electrical Works on Shutdown Periods

Work Locations

The projects are being performed at several locations on the pipeline & Pump stations & Block Valve stations etc. When the pipeline is operating.

Pump Station PT-1, PT-2, PT-3, PT-4,
Intermediate Pigging Stations IPT-1, IPT-2,
Marine Terminal CMT,
Block Valve stations: 51 ea
All along the BTC Co. Crude Oil pipeline Turkish Branch 1.076 km.