TURKEY - İZMİR REFINERY NEW CRUDE OIL OFF-LOADING MARINE TERMINAL FACILITIES

Tekfen Job No:

139

Location:

Aliağa, İzmir, Turkey

Client:

TÜPRAŞ, Turkish Petroleum Refineries Co., Inc.

Contractor:

Tekfen Construction and Installation Co., Inc.

Tekfen Portion:

100%

Commencement:

27/05/1986

Completion:

14/11/1989

Construction of a 1.200 m jetty with berthing capacity of 250.000 DWT for crude oil loading / off-loading facilities and one 120 m long smaller jetty. The main jetty is erected on 136 x 24” and 211 x 40” steel piles with a length of 4.924 m.

The project also includes concrete works, steel fabrication, dredging and excavation works.

Tekfen was responsible for construction works while procurement was directly undertaken by the client.

Total value of the project including procurement of the equipment and materials reached US$ 40 Million.

Materials and equipment supplied by the Client are

Product pipe material; jetty pipes,
Berthing Dolphins,
Breasting Dolphins,
Fire Fighting Systems,
Navigation and Lighting Systems,
Unloading arms, auxiliary systems and automatic & telemetric control systems.